Out-Law Analysis 19 min. read
17 Aug 2023, 9:01 am
‘Set off’, ‘abatement’ and ‘counterclaim’ are all commonly deployed terms in legal arguments concerning the reasons why a party is unwilling to pay for construction work.
For example, faced with a claim for defective work, an employer or main contractor will want to account for this loss in the next, or final, payment certificate. Set off, abatement and counterclaim are the three different potential legal routes in the UK for this process.
This guide will explain the key features of each of these terms, explain the important differences, illustrate these points with some case law examples and common standard form provisions and offer some key practical takeaways.
Set off is a mechanism that permits a party to deduct amounts from sums that would otherwise be due because of a countervailing debt or claim, known as a ‘cross-claim’. Set off commonly occurs when an employer deducts sums from a contractor’s payment certificate due to, for example, defects in the works for the costs of putting them right or for lost income due to the defect. It is a right that arises at law as well as in many standard forms of contract. Those of main importance to the construction industry are:
It is important to note that insolvency set off can also give rise to a right of set off in the construction industry in certain formal insolvency situations. This specialist topic is not covered in detail in this guide. The right to set off is curtailed in the UK by the 1996 Housing Grants, Construction and Regeneration Act, as amended by Part 8 of the 2009 Local Democracy, Economic Development and Construction Act (the Construction Act) and the 1998 Scheme for Construction Contracts, which is also a separate subject in itself.
Legal set off operates in the context of court proceedings, acting as a procedural defence whereby mutual debts, which may be unconnected reciprocal claims which are independent of each other, can be set off against claims brought against a party.
To be available, both the claim and the cross-claim must be “due and payable”, liquidated or ascertainable without valuation or estimation, owed between the same persons and actionable in the English courts. The two claims need not be connected, for example, they might arise under two unrelated contracts.
Equitable set off, on the other hand, occurs when two claims are so closely connected that it would be manifestly unjust to allow one party to enforce its claim without giving credit for the cross-claim of the other party. As with legal set off, both claims must be “due”. Importantly, it is not limited to liquidated claims, unlike legal set off. If the cross-claim is not ascertained, the debtor may deduct a reasonable assessment of the loss, made in good faith.
The table below summarises the differences between legal and equitable set off.
|
Legal |
Equitable |
---|---|---|
Available in litigation only? |
Yes |
No |
Must be liquidated? |
Yes |
No |
Due and payable? |
Yes |
Yes |
Must be mutual? |
Yes |
Yes |
Must be closely connected claims? |
No |
Yes |
Applicable to future or contingent claims? |
No |
No |
Many of the industry’s standard contractual forms crystallise right of set off, although they vary slightly in their approach. The obvious benefit of an express contractual right to set off is that the parties can agree the precise circumstances in which it is applicable, without the need to rely on an implied legal or equitable right. This is another example of the difference between claims under a contract and claims for breach of contract.
Parties may also extend or curtail the situations in which legal and equitable set off are applicable, but cannot exclude the right of insolvency set off. For example, an employer could make provision for a right to set off a claim arising under another unconnected contract with the same contractor, importing the tenets of legal set off without the requirement that it can only be raised in litigation.
The table below sets out set off provisions in the main standard forms used in the UK:
JCT D&B 2011/2016 |
Clause 2.29.2.2 |
Permits the employer to “withhold or deduct liquidated damages at the rate stated in the Contract Particulars.” |
---|---|---|
Clause 2.35 |
Permits the employer to make “an appropriate deduction” from the contract sum in respect of defects, shrinkages or other faults not made good by the contractor. |
|
NEC4 / NEC3 |
Clause 50.3 / 50.2 |
The NEC forms contain no specific provision for set-off, but Clause 50.3 (50.2 in NEC3) states that the amount due in the Project Manager’s assessment takes into account amounts to be paid by or retained from the contractor. |
FIDIC Red Book 1999 / 2017 |
Clause 20.2.7 (2017) / Clause 2.5 (1999) |
Permits set-off by the employer against an amount due to the contractor, subject to compliance with the Clause 20.2 claims procedure. In the 1999 edition, Clause 2.5 permits the employer to set off sums “in connection with the contract” against certified sums, but only once the engineer has agreed or certified any amount owing to the contractor following a claim. |
This case considered what is meant by “manifestly unjust” for equitable set off to apply. The court said: “It is not coherent to have a doctrine of equitable set-off which ignores the need for consideration of aspects of justice and fairness”.
It found that the defendant, by insisting on payment under a supply contract as a pre-condition of returning to work on an installation contract, was “bringing the two contracts into intimate relationship with one another … and that relationship became inseparable and irrevocable” when the claimant brought the installation contract to an end in reliance on the defendant’s poor performance under it, coupled with the defendant’s insistence on payment under the supply contract.
The court held that: “Even if the two contracts had not been connected up to that point, those events brought the two contracts into a close and inseparable relationship with one another and, in my judgment, made it manifestly unjust to enforce payment under the supply contract without taking into account the cross-claim for repudiation of the installation contract.”
Abatement is a close cousin of set off. Both set off and abatement are, in practise, used in construction to prevent the obligation to pay. The main difference is that abatement is usually used to reduce or ‘abate’ the sum due in the first place, as opposed to set off the amount to be paid by identifying that cross claim.
Abatement is restricted to contracts for work or goods, not for professional services. It is only available where there has been a breach of contract for performance of the work, or a breach of warranty in relation to goods. Importantly, it does not apply to claims relating to claims for delay, disruption or damage.
Abatement is available as of right in construction contracts and, in essence, permits a party to defend itself by demonstrating that the subject matter of the payment is worth less than claimed by reason of a breach. Parties may, by agreement, limit or exclude their rights to set off or abate, provided that clear words are used to do so and that to do so would not offend the 1977 Unfair Contract Terms Act.
In this case, the judge set out seven principles of abatement:
This case is a good example of what is insufficient to exclude the right to set off or abate. The court held that an exclusive remedies provision in the IChemE Yellow Book was insufficient to exclude the remedy of abatement.
In this dispute, the court was tasked with answering the question of whether a contractual cap limiting liability applied prior to setting off or after. In this case, which turned on the contractual wording, Rolls-Royce was found to have rightfully terminated its contract with Topalsson and was owed roughly €8 million in termination losses. Topalsson was found to be owed roughly €800,000 for services performed prior to termination. The judge found that the cap applied post set off, hence the full €5m was payable, rather than €4.2m.
It is generally agreed that set off and abatement are a defence, to be used only as a “shield, not as a sword”. However, counterclaims can be both. Counterclaims are thus key features of construction disputes in practise – where a separate claim, albeit between the same parties, can be run together in those same dispute proceedings.
In adjudication, this needs to be done with a ‘counter adjudication’ – particularly where there are issues over payment and ‘pay less’ notices preventing an abatement or set off. Crucially, counterclaims can result in a positive balance for the defendant, as opposed to set off and abatement, which are by nature limited to the amount of the original claim.
The table below sets out the differences between set off, abatement and counterclaim.
|
Set off |
Abatement |
Counterclaim |
---|---|---|---|
Acts solely as a defence? |
Yes |
Yes |
No |
Can result in a positive balance of claim? |
No |
No |
Yes |
Must be liquidated? |
Legal: Yes Equitable: No Contractual: It depends |
Yes |
No |
Applicable to professional services? |
Yes |
No |
Yes |
Must comply with the Construction Act payment provisions? |
Yes |
Yes |
No |
Available in arbitration? |
Legal: No Equitable: Yes Contractual: Yes |
Yes |
Yes |
Set off, abatement and counterclaim are key mechanisms for balancing payment obligations. They are thus an important way of avoiding having to “pay now and argue later”.
All three arise in different ways and have different legal and contractual requirements for a party to be able to rely upon them. As a result, it is important to understand and follow those requirements in practice.
Co-written by Kerry Higgins and Mariam Hassaballah of Pinsent Masons.